FMEA Risk Priority Number.
RPN = Severity × Occurrence × Detection. With AIAG-VDA 2019 Action Priority (AP) — the modern method that replaced raw RPN ranking. Use for both DFMEA and PFMEA.
RPN
—
—
Severity
—
Occurrence
—
Detection
—
—
—
RPN interpretation thresholds
| RPN range | Priority | Action required |
|---|---|---|
| ≥ 200 | CRITICAL | Mandatory action — redesign or process change. Cannot ship product. |
| 120 – 200 | HIGH | Action required — develop containment plan and timeline before next phase. |
| 60 – 120 | MEDIUM | Plan corrective action — address in next continuous improvement cycle. |
| < 60 | LOW | Monitor only — no immediate action required. |
| Severity = 9 or 10 | SAFETY/REG | Action mandatory regardless of RPN — design out the failure mode. |